Month 1 (January 3, 2012) (Start of Phase 1 – 32 beds)
Month 2 (February 2012)
Month 3 (March 2012)
Month 5 (May 2012)
Month 6 (June 2012)
Month 7 (July 13, 2012)
(Certificate of Pre-Occupancy granted by the Ministry of Health)
Month 7 to 10 (July 23 to October 31, 2012) (Start of Phase 2 – 22 beds)
Month 11 (November 6, 2012) (Certificate of Pre-Occupancy granted by the Ministry of Health)
Month 11 (November 19, 2012) (Start of Phase 3 – 25 beds)
Month 14 (February 15, 2013)
(Certificate of Pre-Occupancy granted by the Ministry of Health) (Start of Phase 4 – 11 beds)
Month 17 (May 9, 2013)
(Certificate of Pre-Occupancy granted by the Ministry of Health) (Start of Final Phases 5 & 6 – 14 beds)
Month 19 (July 31, 2013)
(Certificate of Pre-Occupancy granted by the Ministry of Health) Official opening scheduled for September 2013